Audi 100/A6

1990-1997 of release

Repair and car operation



Audi 100/A6
+ 1. Maintenance instruction
+ 2. Maintenance
+ 3. Engines
+ 3.2. Diesel engines
+ 3.3. Removal and partition of engines
+ 4. Cooling system
+ 5. Heating and ventilation
+ 6. Fuel system
- 7. Exhaust system
   7.2. Technical characteristics
   7.3. Collecting system паров fuels
   + 7.4. System of collecting karterny gases
   + 7.5. System of a retsirkulyatsiya of exhaust gases
   7.6. Final collector
   7.7. urbokompressor
   7.8. Intermediate cooler
   7.9. System of production of the fulfilled gases
   7.10. Catalytic converter
+ 8. Systems of start, ignition
+ 9. Transmission
+ 10. Brake system
+ 11. Suspension brackets, steering
+ 12. Body
+ 13. Electric equipment
+ 14. Good advice


ff85f19c

7.9. System of production of the fulfilled gases

GENERAL INFORMATION

The exhaust system consists of a reception pipe, the catalytic converter, an intermediate pipe and the exhaust silencer, an exhaust pipe and the exhaust silencer.

Removal

Each of sections of an exhaust system can be removed separately from the others.

RECEPTION PIPE (INCLUDING the NA CATALYTIC CONVERTER MODELS WITH the ENGINE 1Z and AHU)


Fastening of a reception pipe of an exhaust system

PERFORMANCE ORDER
1. Remove a protective guard from below the engine and a cross-piece behind a transmission.
2. Turn off fixing bolts and fastening elements.
3. Turn off fixing nuts and disconnect a pipe from a final collector.
4. Turn off fixing bolts and remove a reception pipe.

THE CATALYTIC CONVERTER (EXCEPT MODELS WITH THE ENGINE 1Z AND AHU)

PERFORMANCE ORDER
5. Disconnect a reception pipe from the catalytic converter.
6. Turn off fixing bolts and remove the catalytic converter.

INTERMEDIATE PIPE

PERFORMANCE ORDER
7. Turn off fixing bolts and disconnect a pipe from the catalytic
converter and exhaust silencer.
8. Remove an intermediate pipe.

EXHAUST PIPE AND EXHAUST SILENCER

PERFORMANCE ORDER
9. Turn off fixing bolts and an intermediate pipe.
10. Remove the exhaust silencer and a pipe from fastenings.

HEAT-SHIELDING SCREENS

PERFORMANCE ORDER
11. For removal of screens it is necessary to turn off fixing screws.

Installation

Installation is carried out upside-down removals.